The top deck is a via-duct. The
longest span�s viaduct weighed
400T. The pre-cast and post
stressed via duct is supported
at two ends, lifted by cluster
of hyd jacks, hung and traversed
to position over launching
girder. On reaching the
position, via ducts were lowered
at safe controlled speed by hyd
jacks to the right position over
the bearing mounted on erected
pier.
For product details click
here

Hightorque supplied hyd jacks
and power packs. Jacks were
provided with built in load
holding valve. Pumping unit
fitted with speed control
valve/s. All performed
satisfactorily and recorded ZERO
break down till completion of
the project. Traversing and
lowering operations were carried
out keeping pedestrian and
vehicle movement alive. This is
to confirm Hightorque�s
commitment to safety and
reliability. L&T executed the
long stretch of the project in
record time.
|